Blair Airport Construction Project

Blair Airport Construction Project

Project Name: Blair Airport Construction

Project venue: Blair port

Project Steel Pipe Usage: This project is constructed by local large EPC. The customer background is a well-known local builder. It undertakes various government hospitals, banks and other infrastructure projects. This project is in the airport construction of Blair, and needs thick-walled straight seam submerged arc steel pipe.

Specification of Project Steel Pipe: 
355×22×6000mm
650×25×6000mm
650×32×6000mm
Project Steel Tube Completion Time: August 2018
Project start-up and installation time: October 2018
Project Tripartite Inspection Contents: Physical and Chemical Experiments of Product Sampling
and Final Inspection of Size and Appearance